POLITIDEX

☀️ Sunlight Governance

Sunlight Governance

Some systems you can’t opt out of: the power company, the water utility, the roads and the programs your taxes pay for. Sunlight Governance means a full public ledger for them — every cost, every profit and every contract in one open place — so everyone can see the whole picture, head to toe.

What a full ledger shows

Your bill, two ways

🔒 Hidden: one number
📖 Open: every part labelled

A picture example. The blocks are not to scale and are not any one utility’s figures.

Before and after: one real rate case

🔒 Hidden costs

  • Your bill goes up about $4.31 a month.
  • What was asked for? Not on the bill.
  • Why this amount? Not on the bill.
  • Which contracts? Not on the bill.

📖 Full open ledger

  • Bill: +$4.31 a month (4.7%) in 2025.
  • Asked for: $667.3 million.
  • Approved: $87.2 million; allowed profit rate 9.375%.
  • Wind contract price: ██████ still confidential.

Figures from the Utah Public Service Commission’s April 25, 2025 order in Rocky Mountain Power’s rate case. The redacted line is the part the full ledger would still open.

Asked for vs. approved

Rocky Mountain Power rate increase, Utah PSC Docket No. 24-035-04 (millions of dollars)
Bar graph. Original request: $667.3 million. Final revised request: $330.2 million. Approved increase: $87.2 million. Original request Original request: $667.3 million $667.3M Final revised request Final revised request: $330.2 million $330.2M Approved Approved increase: $87.2 million $87.2M

When the request and the order sit side by side, anyone can see the gap — and ask what is behind it.

The same idea, later

The same open ledger can later support community programs, where who takes part and what is paid back stay visible to everyone.

First working example Rocky Mountain Power rate case → The docket, what was asked for vs. what was ordered, the five parts of the record that stayed confidential, and every source document.

Sub-tags

Both start with the same three-question Market-Power Test and point back to the Rocky Mountain Power example.

Next step: ask Rocky Mountain Power to publish one confidential contract — a public version of the Cedar Springs IV wind contract’s pricing terms.

Sunlight Governance is a filing label for transparency, not a verdict on any utility, regulator or official. Search the record.